Housing

Sadiq Khan owes London a housing timetable

His March 2026 reply promised regular reporting, but did not envisage publishing the timetable Londoners would need to judge progress.

London’s Social and Affordable Homes Programme 2026–36 is the sort of commitment a government should be able to make. City Hall’s February 2026 funding guidance set out funding of up to £11.7 billion for homes including social rent and shared ownership. A long settlement gives housing providers time to prepare work that cannot sensibly be improvised from one annual budget to the next. I favour giving them that certainty, and I want the Mayor to explain what London should receive along the way.

In his 17 March 2026 reply to the London Assembly’s Budget and Performance Committee, Sadiq Khan said he would tell the Committee the programme’s overall delivery targets once agreed with the Government. He would also continue publishing quarterly and annual data on starts and completions. But he did not anticipate publishing the interim milestones: the expected numbers of starts and completions by specified dates. He said disclosure could influence the market and reduce the number of homes obtainable with the available grant. This was his stated approach in March, while the delivery plan still had to be established.

That distinction matters. A record of what has happened does not tell us whether it happened when expected. Nor are starts and completions interchangeable: a programme could report progress on starting homes while falling behind its expected completions. Without published expectations for each, it is harder for voters to distinguish a programme advancing as planned from one accumulating delays. Supporting a building programme should include being able to see where it needs help, rather than discovering too late that its promised output has become unattainable.

There is a plausible commercial objection. Suppose, for example, a provider knows City Hall needs an agreement quickly to meet a published target and uses that pressure to seek a larger grant. Publishing every project’s negotiating position would be a poor way to buy more homes. But an annual forecast for the programme as a whole need not disclose the terms being discussed on a particular development. The Mayor should explain what harm even that broader forecast would cause, and whether a range or a temporary delay in publication could avoid it.

The programme was not designed to proceed without schedules. The February guidance said providers’ contracts would require agreed project milestones, monitored by the GLA. Those contractual dates are distinct from the public annual expectations I am proposing. They do, however, show that a long programme can be managed against intermediate commitments. The public should have a useful standard for judging the Mayor’s performance too, without needing access to every contract.

Such a standard must allow forecasts to change. The housing department’s January 2026 annual report describes renegotiation of the earlier England-wide 2021–26 programme after higher construction costs and other pressures on social landlords’ finances. It also records that there were no delivery targets for individual years. Revising a forecast can be responsible administration. Keeping the previous forecast visible allows the public to judge what has changed. A delay that preserves the eventual number of homes and a cut in that number deserve different explanations.

For London’s new programme, I would publish annual expectations once agreed, with separate figures for starts and completions, and put the reported results beside them. Each revision should retain the previous forecast and explain whether homes have moved to a later year or been removed from the expected total. Where disclosure would damage a live negotiation, City Hall should identify the risk as far as it can and set a date to reconsider withholding the figures.

The February guidance’s delivery criteria allowed projects to start by March 2036 and complete by March 2039, while giving priority to early delivery, including completions by March 2029. The 2036 and 2039 dates are outer deadlines, not the expected duration of every project. They make interim scrutiny more necessary: a final reckoning in 2039 leaves too much responsibility to whoever happens to hold office then. Khan’s March response offered a way to count results. He should also accept a timetable that lets London judge his administration’s contribution while he can still answer for it.